July 2018

Installation of underground commodities continues Unit 3 containment ECS-ES-2 switchgear in Unit 3 annex building Unit 3 auxiliary building Unit 3 auxiliary building Unit 3 stargate assemblies in first bay of turbine building Vogtle 3 and 4 currently employs over 6,000 workers Unit 3 containment Unit 3 Unit 3 turbine building Unit 3 Installation of underground commodities continues on the east side of Unit 4 Unit 4 Unit 4 turbine building Unit 4 Unit 3 turbine building Progress continues outisde of Unit 3 containment Unit 3 shield building progresses Electrical Penetration in Unit 3 shield building A major concrete placement lasting 8 continuous hours was made inside Unit 3 shield building